Annapolis, Maryland, January 14, 2026
The City of Annapolis has launched the first phase of the City Dock Resiliency and Revitalization Project aimed at safeguarding its historic waterfront from flooding. The $88 million project will temporarily reduce parking availability along Dock Street, raising concerns among local businesses regarding customer access and revenue decline. While construction is scheduled through 2027, the city reassures that all businesses will remain open, encouraging community support during this transitional phase as they work towards a more resilient waterfront.
Annapolis Begins City Dock Construction Amid Parking Reductions and Business Concerns
Annapolis, Maryland – The City of Annapolis has commenced the first phase of the City Dock Resiliency and Revitalization Project, aiming to protect the historic waterfront from frequent flooding. This initiative involves significant construction that will temporarily reduce parking availability and may impact local businesses.
Project Overview
The City Dock area has been prone to regular flooding, affecting businesses, homes, and infrastructure. The $88 million project seeks to address these challenges by elevating the waterfront, installing flood barriers, and creating a raised park to mitigate future flooding events. Construction is scheduled in phases through 2027, with the first phase focusing on bulkhead replacement, utility work, and rebricking. During this period, parking along Dock Street will be limited due to extended fencing. However, the city assures that all businesses will remain open during construction.
Impact on Parking and Local Businesses
As construction progresses, parking spaces along Dock Street will be temporarily blocked off, leading to concerns among local business owners about potential declines in customer traffic. Some businesses have already reported a decrease in revenue due to the loss of parking and the ongoing construction.
Background Context
The City Dock Resiliency and Revitalization Project has been in development for several years, with extensive community engagement and planning. The project aims to protect downtown Annapolis from frequent flooding, enhance public access, and improve the visitor experience. Funding for the project includes a $24 million concession payment from the Hillman Garage redevelopment, state and federal grants, and directed spending.
While the project is expected to provide long-term benefits, the city acknowledges the temporary inconveniences during construction and is working to minimize disruptions to residents and businesses.
Community Engagement and Economic Growth
The City Dock project not only aims at infrastructural improvement but also embodies a vision of community resilience. Local leaders are optimistic that, despite the short-term challenges, this project will ultimately enhance the economic landscape of Annapolis by attracting more visitors and boosting small business opportunities in the long run.
Conclusion
In summary, Annapolis’s City Dock Resiliency and Revitalization Project represents a significant step towards safeguarding the city’s waterfront while also addressing the immediate concerns of local businesses affected by construction. As community members rally together to support entrepreneurs during this transitional phase, there is hope that the results will pave the way for a more vibrant, flood-resilient future. Residents are encouraged to continue supporting local businesses as they adapt to the temporary challenges posed by this essential development project.
Frequently Asked Questions
- What is the City Dock Resiliency and Revitalization Project?
- The City Dock Resiliency and Revitalization Project is an $88 million initiative aimed at protecting Annapolis’s historic waterfront from frequent flooding. The project involves elevating the waterfront, installing flood barriers, and creating a raised park to mitigate future flooding events. Construction is scheduled in phases through 2027.
- How will the construction affect parking in the area?
- During construction, parking spaces along Dock Street will be temporarily blocked off due to extended fencing. This reduction in parking availability may impact local businesses and customer traffic.
- Will businesses remain open during construction?
- Yes, all businesses along Dock Street will remain open during construction. The city is working to minimize disruptions and ensure that businesses can continue operations throughout the project.
- What is the expected timeline for the project?
- The project is scheduled in phases through 2027, with the first phase focusing on bulkhead replacement, utility work, and rebricking. Subsequent phases will address additional aspects of the revitalization plan.
- How is the project being funded?
- Funding for the project includes a $24 million concession payment from the Hillman Garage redevelopment, state and federal grants, and directed spending. The city has secured substantial funding to support the project’s goals.
| Key Feature | Description |
|---|---|
| Project Name | City Dock Resiliency and Revitalization Project |
| Location | Annapolis, Maryland |
| Project Cost | $88 million |
| Construction Phases | Scheduled through 2027 |
| Impact on Parking | Temporary reduction in parking availability along Dock Street |
| Business Operations | All businesses along Dock Street will remain open during construction |
| Funding Sources | $24 million concession payment from Hillman Garage redevelopment, state and federal grants, and directed spending |
Deeper Dive: News & Info About This Topic
HERE Resources
Outgoing Annapolis Mayor Reflects on Accomplishments
Major Construction on I-95 Cover Extension in Philadelphia
Construction Begins on America’s First Arctic Deepwater Port
Author: STAFF HERE BALTIMORE WRITER
The BALTIMORE STAFF WRITER represents the experienced team at HEREBaltimore.com, your go-to source for actionable local news and information in Baltimore, Baltimore County, and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the Baltimore Book Festival, Preakness Stakes, and Artscape. Our coverage extends to key organizations like the Baltimore Chamber of Commerce and Visit Baltimore, plus leading businesses in shipping and healthcare that power the local economy such as the Port of Baltimore and Johns Hopkins Medicine. As part of the broader HERE network, we provide comprehensive, credible insights into Maryland's dynamic landscape.